Following months of preparation, including clearing and asbestos removal, the mechanical demolition phase of the building is now underway. This new stage is highly visible and signifies the transformation of the area.
Teams are employing specialized machinery equipped with a concrete nibbler to dismantle the structure floor by floor. This method aims to control nuisances and ensure optimal safety for residents and workers.
Materials from the deconstruction are sorted and valorized to promote recycling. For instance, crushed concrete will be used to fill the site after foundation purging, minimizing the operation's environmental impact.
Ultimately, the demolition of the Goya building will free up land to support the neighborhood's transformation and prepare for future developments within Bellefontaine's urban renewal plan. Demolition, foundation purging, and land backfilling are expected to be completed by late December 2026.